# HRIStudio Thesis Implementation - Fall 2025
|
|
|
|
**Sean O'Connor - CS Honors Thesis**
|
|
**Advisor**: L. Felipe Perrone
|
|
**Defense**: April 2026
|
|
|
|
## Implementation Status
|
|
|
|
Core platform infrastructure exists but MVP requires wizard interface implementation and robot control integration for functional trials.
|
|
|
|
## Fall Development Sprint (10-12 weeks)
|
|
|
|
| Sprint | Focus Area | Key Tasks | Success Metric |
|
|
|--------|------------|-----------|----------------|
|
|
| 1 (3 weeks) | Wizard Interface MVP | Trial control interface<br/>Step navigation<br/>Action execution buttons | Functional wizard interface for trial control |
|
|
| 2 (4 weeks) | Robot Integration | NAO6 API integration<br/>Basic action implementation<br/>Error handling and recovery | Wizard button → robot action |
|
|
| 3 (3 weeks) | Real-time Infrastructure | WebSocket server implementation<br/>Multi-client session management<br/>Event broadcasting system | Multiple users connected to live trial |
|
|
| 4 (2 weeks) | Integration Testing | Complete workflow validation<br/>Reliability testing<br/>Mock robot mode | 30-minute trials without crashes |
|
|
|
|
## User Study Preparation (4-5 weeks)
|
|
|
|
| Task Category | Deliverables | Effort |
|
|
|---------------|--------------|--------|
|
|
| Study Design | Reference experiment selection<br/>Equivalent implementations (HRIStudio + Choregraphe)<br/>Protocol validation | 3 weeks |
|
|
| Research Setup | IRB application submission<br/>Training material development<br/>Participant recruitment | 2 weeks |
|
|
|
|
## MVP Implementation Priorities
|
|
|
|
| Priority | Component | Current State | Target State |
|
|
|----------|-----------|---------------|-------------|
|
|
| **P0** | Wizard Interface | Design exists, needs implementation | Functional trial control interface |
|
|
| **P0** | Robot Control | Simulated responses only | Live NAO6 hardware control |
|
|
| **P0** | Real-time Communication | Client hooks exist, no server | Multi-user live trial coordination |
|
|
| **P1** | Trial Execution | Basic framework exists | Integrated with wizard + robot hardware |
|
|
| **P2** | Data Capture | Basic logging | Comprehensive real-time events |
|
|
|
|
## Success Criteria by Phase
|
|
|
|
### MVP Complete (10-12 weeks)
|
|
- [ ] Wizard interface allows trial control and step navigation
|
|
- [ ] Psychology researcher clicks interface → NAO6 performs action
|
|
- [ ] Multiple observers watch trial with live updates
|
|
- [ ] System remains stable during full experimental sessions
|
|
- [ ] All trial events captured with timestamps
|
|
|
|
### Study Ready (14-17 weeks)
|
|
- [ ] Reference experiment works identically in both platforms
|
|
- [ ] IRB approval obtained for comparative study
|
|
- [ ] 10-12 participants recruited from target disciplines
|
|
- [ ] Platform validated with non-technical users
|
|
|
|
## MVP Backlog - Priority Breakdown
|
|
|
|
### P0 - Critical MVP Features
|
|
| Story | Effort | Definition of Done |
|
|
|-------|--------|-------------------|
|
|
| Wizard interface trial control | 2 weeks | Interface for starting/stopping trials, navigating steps |
|
|
| Action execution buttons | 1 week | Buttons for robot actions with real-time feedback |
|
|
| NAO6 API integration | 3 weeks | Successfully connect to NAO6, execute basic commands |
|
|
| Basic robot actions | 2 weeks | Speech, movement, posture actions working |
|
|
| WebSocket server implementation | 2 weeks | Server accepts connections, handles authentication |
|
|
| Multi-client session management | 1 week | Multiple users can join same trial session |
|
|
|
|
### P1 - High Priority Features
|
|
| Story | Effort | Definition of Done |
|
|
|-------|--------|-------------------|
|
|
| Event broadcasting system | 1 week | Actions broadcast to all connected clients |
|
|
| Robot status monitoring | 1 week | Connection status, error detection |
|
|
| End-to-end workflow testing | 1.5 weeks | Complete trial execution with real robot |
|
|
|
|
### P2 - Backlog (Post-MVP)
|
|
| Story | Effort | Definition of Done |
|
|
|-------|--------|-------------------|
|
|
| Connection recovery mechanisms | 1 week | Auto-reconnect on disconnect, graceful fallback |
|
|
| Mock robot development mode | 0.5 weeks | Development without hardware dependency |
|
|
| Performance optimization | 0.5 weeks | Response times under acceptable thresholds |
|
|
| Advanced data capture | 1 week | Comprehensive real-time event logging |
|
|
|
|
## User Study Framework
|
|
|
|
**Participants**: 10-12 researchers from Psychology/Education
|
|
**Task**: Recreate published HRI experiment
|
|
**Comparison**: HRIStudio (experimental) vs Choregraphe (control)
|
|
**Measures**: Protocol accuracy, completion time, user experience ratings
|
|
|
|
## Implementation Strategy
|
|
|
|
Core platform infrastructure exists but wizard interface needs full implementation alongside robot integration. Focus on MVP that enables basic trial execution with real robot control.
|
|
|
|
**Critical Path**: Wizard interface → WebSocket server → NAO6 integration → end-to-end testing → user study execution |